Lake Tahoe road work schedule for November 29 - December 4

There is no road work scheduled for the South Shore this week. Here are the current projects around the lake:

Interstate 80 (Placer County) from Brace Road to Magra Road: Work continues on a $36 million project to increase the vertical clearance of nine bridge structures in south Placer County to 16 feet, 6 inches. The vertical clearance will be increased on seven structures by lifting the existing bridge deck and the other two will have the roadway below dug down. More information on the project is available at www.raise80.com

Lake Tahoe road work schedule for November 22-28

Because of the Thanksgiving holiday, most lane closures will be restricted from 6 a.m. Wednesday, November 25 until 8 p.m. Sunday, November 29.

LONG-TERM PROJECTS

Lake Tahoe road work schedule for November 15-21

LONG-TERM PROJECTS

State Route 89 (Placer County): Work is in winter suspension on a $70.1 million project from Tahoma to the "Y" junction with State Route 28 in Tahoe City on Lake Tahoe’s West Shore that will upgrade storm water drainage and treatment systems, add curb and gutter, resurface and realign the road, add new left-turn pockets and widen shoulders on a 9-mile stretch of the highway. Completion is expected in fall 2016.

Lake Tahoe road work schedule for November 8 - 14

LONG-TERM PROJECTS

State Route 89 (Placer County): Work continues on a $70.1 million project from Tahoma to the "Y" junction with State Route 28 in Tahoe City on Lake Tahoe’s West Shore that will upgrade storm water drainage and treatment systems, add curb and gutter, resurface and realign the road, add new left-turn pockets and widen shoulders on a 9-mile stretch of the highway. Completion is expected in fall 2016.

Lake Tahoe road work schedule for November 1 - 7

LONG-TERM PROJECTS

State Route 89 (Placer County): Work continues on a $70.1 million project from Tahoma to the "Y" junction with State Route 28 in Tahoe City on Lake Tahoe’s West Shore that will upgrade storm water drainage and treatment systems, add curb and gutter, resurface and realign the road, add new left-turn pockets and widen shoulders on a 9-mile stretch of the highway. Completion is expected in fall 2016.

Lake Tahoe road work schedule for October 25 - 31

LONG-TERM PROJECTS

State Route 89 (Placer County): Work continues on a $70.1 million project from Tahoma to the "Y" junction with State Route 28 in Tahoe City on Lake Tahoe’s West Shore that will upgrade storm water drainage and treatment systems, add curb and gutter, resurface and realign the road, add new left-turn pockets and widen shoulders on a 9-mile stretch of the highway. Completion is expected in fall 2016.

City addressing complaints about Caltrans projects in South Lake Tahoe

There's an old joke about the seasons in Lake Tahoe: There are two seasons in Lake Tahoe. Winter, and Road Construction.

While the "winter" comment may not be as it once was, there is no question about "road construction" as it now goes from May through October.

Part of living in the mountains is sharing our best weather months with construction workers, road controls and traffic cones. Residents get that. But what drivers went through during the 2015 construction on highways 50 and 89 was not only inexcusable, it was preventable.

Lake Tahoe road work schedule for October 18 - 24, 2015

LONG-TERM PROJECTS

State Route 89 (Placer County): Work continues on a $70.1 million project from Tahoma to the "Y" junction with State Route 28 in Tahoe City on Lake Tahoe’s West Shore that will upgrade storm water drainage and treatment systems, add curb and gutter, resurface and realign the road, add new left-turn pockets and widen shoulders on a 9-mile stretch of the highway. Completion is expected in fall 2016.

Lake Tahoe road work schedule for October 11 - 17, 2015

LONG-TERM PROJECTS

State Route 89 (Placer County): Work continues on a $70.1 million project from Tahoma to the "Y" junction with State Route 28 in Tahoe City on Lake Tahoe’s West Shore that will upgrade storm water drainage and treatment systems, add curb and gutter, resurface and realign the road, add new left-turn pockets and widen shoulders on a 9-mile stretch of the highway. Completion is expected in fall 2016.

Lake Tahoe road work schedule for October 5-10, 2015

LONG-TERM PROJECTS

State Route 89 (Placer County): Work continues on a $70.1 million project from Tahoma to the "Y" junction with State Route 28 in Tahoe City on Lake Tahoe’s West Shore that will upgrade storm water drainage and treatment systems, add curb and gutter, resurface and realign the road, add new left-turn pockets and widen shoulders on a 9-mile stretch of the highway. Completion is expected in fall 2016.

Lake Tahoe road work schedule for September 27 - October 3

LONG-TERM PROJECTS

State Route 89 (Placer County): Work continues on a $70.1 million project from Tahoma to the "Y" junction with State Route 28 in Tahoe City on Lake Tahoe’s West Shore that will upgrade storm water drainage and treatment systems, add curb and gutter, resurface and realign the road, add new left-turn pockets and widen shoulders on a 9-mile stretch of the highway. Completion is expected in fall 2016.

Lake Tahoe road work schedule for September 20 - 26, 2015

LONG-TERM PROJECTS
State Route 89 (Placer County): Work continues on a $70.1 million project from Tahoma to the "Y" junction with State Route 28 in Tahoe City on Lake Tahoe’s West Shore that will upgrade storm water drainage and treatment systems, add curb and gutter, resurface and realign the road, add new left-turn pockets and widen shoulders on a 9-mile stretch of the highway. Completion is expected in fall 2016.

Lake Tahoe road work schedule for September 13 - 19, 2015

LONG-TERM PROJECTS

State Route 89 (Placer County): Work continues on a $70.1 million project from Tahoma to the "Y" junction with State Route 28 in Tahoe City on Lake Tahoe’s West Shore that will upgrade storm water drainage and treatment systems, add curb and gutter, resurface and realign the road, add new left-turn pockets and widen shoulders on a 9-mile stretch of the highway. Completion is expected in fall 2016.

Lake Tahoe road work schedule for September 6 - September 12

LONG-TERM PROJECTS

State Route 89 (Placer County): Work continues on a $70.1 million project from Tahoma to the "Y" junction with State Route 28 in Tahoe City on Lake Tahoe’s West Shore that will upgrade storm water drainage and treatment systems, add curb and gutter, resurface and realign the road, add new left-turn pockets and widen shoulders on a 9-mile stretch of the highway. Completion is expected in fall 2016.

Lake Tahoe road work schedule for August 30 - September 5

LONG-TERM PROJECTS

State Route 89 (Placer County): Work continues on a $70.1 million project from Tahoma to the "Y" junction with State Route 28 in Tahoe City on Lake Tahoe’s West Shore that will upgrade storm water drainage and treatment systems, add curb and gutter, resurface and realign the road, add new left-turn pockets and widen shoulders on a 9-mile stretch of the highway. Completion is expected in fall 2016.

Lake Tahoe road work schedule for August 23 - August 29

LONG-TERM PROJECTS

State Route 89 (Placer County): Work continues on a $70.1 million project from Tahoma to the "Y" junction with State Route 28 in Tahoe City on Lake Tahoe’s West Shore that will upgrade storm water drainage and treatment systems, add curb and gutter, resurface and realign the road, add new left-turn pockets and widen shoulders on a 9-mile stretch of the highway. Completion is expected in fall 2016.

Lake Tahoe road work schedule for August 16 - 22

LONG-TERM PROJECTS

State Route 89 (Placer County): Work continues on a $70.1 million project from Tahoma to the "Y" junction with State Route 28 in Tahoe City on Lake Tahoe’s West Shore that will upgrade storm water drainage and treatment systems, add curb and gutter, resurface and realign the road, add new left-turn pockets and widen shoulders on a 9-mile stretch of the highway. Completion is expected in fall 2016.

Travel in Meyers to be slow moving through Thursday

If you've had to travel on Highway 50 through Meyers this week you've most likely been stuck in one spot for quite a while.

Due to a grinding and paving job on U.S. Highway 50 from Apache Avenue to Country Club Drive in Meyers, motorists have found one lane of controlled traffic each day from from 7 a.m. to 6 p.m. On Monday, the traffic back up started in Meyers and went past the Tahoe Valley Airport.

The "local's way" on Pioneer Trail is affected with the controlled traffic. For those heading over Echo Summit, it will be easier to take Lake Tahoe Blvd. to North Upper Truckee Road.

Overnight roadwork to affect travelers on U.S. 395 south of Carson City

The Nevada Department of Transportation will begin overnight work to apply a top sealant coating to U.S. 395 between south Carson City and Gardnerville.

Lake Tahoe road work schedule for August 9 - 15

LONG-TERM PROJECTS
State Route 89 (Placer County): Work continues on a $70.1 million project from Tahoma to the "Y" junction with State Route 28 in Tahoe City on Lake Tahoe’s West Shore that will upgrade storm water drainage and treatment systems, add curb and gutter, resurface and realign the road, add new left-turn pockets and widen shoulders on a 9-mile stretch of the highway. Completion is expected in fall 2016.

Lake Tahoe road work schedule for August 2 - 8

LONG-TERM PROJECTS

State Route 89 (Placer County): Work continues on a $70.1 million project from Tahoma to the "Y" junction with State Route 28 in Tahoe City on Lake Tahoe’s West Shore that will upgrade storm water drainage and treatment systems, add curb and gutter, resurface and realign the road, add new left-turn pockets and widen shoulders on a 9-mile stretch of the highway. Completion is expected in fall 2016.

Lake Tahoe road work schedule for July 27 - August 1

LONG-TERM PROJECTS
State Route 89 (Placer County): Work continues on a $70.1 million project from Tahoma to the "Y" junction with State Route 28 in Tahoe City on Lake Tahoe’s West Shore that will upgrade storm water drainage and treatment systems, add curb and gutter, resurface and realign the road, add new left-turn pockets and widen shoulders on a 9-mile stretch of the highway. Completion is expected in fall 2016.

Lake Tahoe road work schedule for July 20 - July 25

Long Term Projects

State Route 89 (Placer County): Work continues on a $70.1 million project from Tahoma to the "Y" junction with State Route 28 in Tahoe City on Lake Tahoe’s West Shore that will upgrade storm water drainage and treatment systems, add curb and gutter, resurface and realign the road, add new left-turn pockets and widen shoulders on a 9-mile stretch of the highway. Completion is expected in fall 2016.

Lake Tahoe road work schedule for July 12-18

LONG-TERM PROJECTS

State Route 89 (Placer County): Work continues on a $70.1 million project from Tahoma to the "Y" junction with State Route 28 in Tahoe City on Lake Tahoe’s West Shore that will upgrade storm water drainage and treatment systems, add curb and gutter, resurface and realign the road, add new left-turn pockets and widen shoulders on a 9-mile stretch of the highway. Completion is expected in fall 2016.

Lake Tahoe road work schedule for June 29 - July 2

Due to the increase of travelers expected in the Lake Tahoe basin, all road work projects will end for the week on Thursday, July 2.

On the South Shore:

Lake Tahoe road work schedule for June 21 - June 27

Here is a list of road projects around the Lake Tahoe basin.

U.S. Highway 50 (El Dorado County) from the junction with State Route 89 to 2nd Street in South Lake Tahoe: Eastbound motorists can expect alternating lane closures from 7 p.m. to 7 a.m. Monday through Friday for gas line relocation work. Eastbound motorists can also expect the right shoulder closed at the same location from 7 a.m. to 7 p.m. for trenching.

Lake Tahoe road work schedule for June 14 - June 20

Here is a list of road projects around the Lake Tahoe basin.

U.S. Highway 50 (El Dorado County) from the junction with State Route 89 to 3rd Street in South Lake Tahoe: Eastbound motorists can expect alternating lane closures around the clock from 7 a.m. Monday to 7 a.m. Friday for gas line relocation work.

Lake Tahoe road work schedule for June 7 - June 12

Here is a list of road projects around the Lake Tahoe basin.

U.S. Highway 50 (El Dorado County) from the junction with State Route 89 to 2nd Street in South Lake Tahoe: Eastbound motorists can expect alternating lane closures from 5 p.m. to 11 a.m. Monday through Friday for gas line relocation work.

South Lake Tahoe roadwork report

Here is a list of road projects around the Lake Tahoe basin.

Project: State Route 89 (El Dorado County): Work continues on a $25 million project from the "Y" junction with U.S. Highway 50 in South Lake Tahoe to Cascade Road, north of Camp Richardson. Curb, gutter and sidewalks will be added in the 1.1-mile four-lane section, and the highway will be widened in the two-lane section to Visitor Center Road to provide 4-foot paved shoulders on each side. Drainage systems are also being built and the roadway will be resurfaced. Completion is expected by spring 2017.

Early morning closure of Highway 50 in El Dorado Hills Sunday

Highway 50 through El Dorado Hills will be closed early Sunday morning as the county's transportation division continues work on the Silva Valley Interchange Project. They will be blasting on the north side of the freeway.

There will be full closures of both directions of U.S. 50 between El Dorado Hills Boulevard and Bass Lake Road, as well as closures of the Latrobe Road on-ramp to eastbound U.S. Highway 50, the Bass Lake Road on-ramp to westbound U.S. Highway 50, and White Rock Road between Valley View Parkway and Entrada Circle.

Closures are as follows:

Lake Tahoe road work schedule for May 26 - May 29

Here is the Lake Tahoe area road report for the week of May 26-29, 2015:

State Route 89 (El Dorado/Placer County) from Wilson Avenue to Elm Street: Motorists can expect one-way traffic control from 7 a.m. to 5:30 p.m. Wednesday and Thursday and 7 a.m. to noon Friday for bump grinding. Motorists can also expect one-way traffic from McKinney Drive to Madden Creek around the clock from 8 p.m. Tuesday to noon Friday for roadway excavation.

Lake Tahoe area road report for May 3 through May 10

Now that weather is favorable for roadwork, Caltrans and NDot have begun their projects around Lake Tahoe and the surrounding areas.

Long term projects:

State Route 89 (Placer County): Work continues on a $70.1 million project from Tahoma to the "Y" junction with State Route 28 in Tahoe City on Lake Tahoe's West Shore that will upgrade storm water drainage and treatment systems, add curb and gutter, resurface and realign the road, add new left-turn pockets and widen shoulders on a 9-mile stretch of the highway. Completion is expected in fall 2016.

Highway 50 to be closed in both directions in El Dorado Hills

Visitors in South Lake Tahoe this weekend should plan on staying in town longer Sunday so they aren't affected by major road work in El Dorado Hills. Travelers headed to the South Shore will need to be prepared as well. Early morning closures of Highway 50 will affect both lanes of traffic between South Lake Tahoe and Sacramento.

Highway 89 construction this summer worries business owners

While the summertime tourist to South Lake Tahoe should only be slightly affected, business owners along Highway 89 are worried about their livelihood with overnight road construction and blocked driveways.

During Thursday evening's Caltrans informational meeting at South Tahoe High, several owners of lodging properties, restaurants, sports and retail stores spoke about their concerns during the project which will last from mid-April to mid-October in 2015 and could even extend into the 2017 building season.

Road work continues in South Lake Tahoe this week

South Lake Tahoe motorists can expect one-way traffic control this week, from Monday through Thursday, 7 a.m. to 5 p.m. on Highway 50 from Airport Road to F Street. This stretch of road is getting erosion control and paving done.

This is part of a $12.1 million water-quality and roadway improvement project from the "Y" intersection of Highways 50 and 89 to the South Lake Tahoe Airport adding curb and gutter, sidewalks, new drainage systems and repaving the highway.

Completion is expected this fall.

South Lake Tahoe's Loop Road Project Update

The US 50/South Shore Community Revitalization Project, also known as the Loop Road Project, is halfway through an Environmental Impact Study which should be released in about nine months.

Bicyclist flown to Renown after being struck by utility truck

A 25-year-old man riding a bicycle was flown to Renown Medical Center in Reno early Tuesday morning after being hit by a utility truck, South Lake Tahoe police report.

The bicyclist, Donovan Boling, sustained significant injuries in the accident, reported at 2:45 a.m. in the area of Wildwood Avenue in South Lake Tahoe. The 29-year-old driver of the truck told South Lake Tahoe police that he didn't see the bicyclist when the accident happened. The bicyclist was reported to not being wearing a helmet.

Road work to cause delays on Hwy. 50 near Shingle Springs

LETTER TO THE EDITOR: Road work should be done at night

It took me an hour to go from Sierra Boulevard to Stateline to pick up my wife from work and back again. This is usually a 15-minute round trip, which now takes an hour, sometimes more. Pioneer Tra...

Fishing report through Sept. 21

Here is the fishing report for the week through Sept. 21. The report covers Nevada, Northern California, Southern Oregon and the Sierra.