kings beach

Letter: Caltrans proposes roundabout at 50/89 intersection in Meyers

The California Department of Transportation (Caltrans) District 3 is developing a safety project that proposes to construct a roundabout at the intersection of U.S. Highway 50 and State Highway 89 in Meyers beginning in 2018. The department has looked at several options at this location and has identified a roundabout as the preferred alternative to address safety concerns and improve traffic flow.

Lake Tahoe area roadwork schedule May 22 - May 28

NOTE: Most traffic-interfering work will be limited from 6 a.m. Friday until 10 p.m. Monday, May 30 for the Memorial Day weekend.

LONG-TERM PROJECTS

State Route 89 (Placer County): Work continues on a $70.1 million project from Tahoma to just north of Granlibakken Road in Tahoe City that is upgrading storm water drainage and treatment systems, adding curb and gutter, resurfacing and realigning the road, adding new left-turn pockets and widening shoulders on an 8-mile stretch of the highway. Completion is expected by summer 2017.

Spectator's guide to Amgen Tour of California in South Lake Tahoe

WHO:
Spectators, volunteers, residents, visitors, businesses, sponsors, media, and cycling enthusiasts

WHAT:
Amgen Tour of California returns to Lake Tahoe, May 19:
Men’s Stage 5 races 132.4 miles from Lodi to South Lake Tahoe
Women’s Stage 1 start/finish in South Shore 72.7 mile circumnavigation of the lake

WHERE:
Race headquarters: Heavenly Mountain Resort California Base Lodge
3860 Saddle Rd, South Lake Tahoe, CA 96150

WHEN:
Thursday, May 19 from 10 a.m. – 4:30 p.m.

Lake Tahoe road work schedule for May 15-21, 2016

LONG-TERM PROJECTS

State Route 89 (Placer County): Work continues on a $70.1 million project from Tahoma to just north of Granlibakken Road in Tahoe City that is upgrading storm water drainage and treatment systems, adding curb and gutter, resurfacing and realigning the road, adding new left-turn pockets and widening shoulders on an 8-mile stretch of the highway. Completion is expected by summer 2017.

Lake Tahoe area roadwork for week of May 9 - 14

LONG-TERM PROJECTS
State Route 89 (Placer County): Work has resumed on a $70.1 million project from Tahoma to just north of Granlibakken Road in Tahoe City that is upgrading storm water drainage and treatment systems, adding curb and gutter, resurfacing and realigning the road, adding new left-turn pockets and widening shoulders on an 8-mile stretch of the highway. Completion is expected by spring 2017.

Open houses held to get public input on Tahoe Transportation Plan

Event Date: 
May 24, 2016 - 5:00pm

Lake Tahoe’s two regional bi-state agencies for transportation, the Tahoe Regional Planning Agency (TRPA) and Tahoe Transportation District (TTD), are inviting the public to attend interactive open houses this month to learn more about draft proposals to improve Tahoe’s highway corridors and share their ideas and input.

The open houses are Tuesday, May 17 at the North Tahoe Events Center in Kings Beach, and Tuesday, May 24 at the Lake Tahoe Resort Hotel in South Lake Tahoe. Both are from 5:00 p.m. to 7:00 p.m.

Lake Tahoe area roadwork for week of May 1 - May 6

LONG-TERM PROJECTS
State Route 89 (Placer County): Work has resumed on a $70.1 million project from Tahoma to just north of Granlibakken Road in Tahoe City that is upgrading storm water drainage and treatment systems, adding curb and gutter, resurfacing and realigning the road, adding new left-turn pockets and widening shoulders on an 8-mile stretch of the highway. Completion is expected by spring 2017.

Lake Tahoe basin roadwork schedule for April 24-30

Caltrans long-term and short-term roadwork projects around the Lake Tahoe Basin:

LONG-TERM PROJECTS

Construction work resumes on Tahoe Basin highways

The 2016 construction season in the Tahoe Basin will get under way next week with work resuming on a multi-year State Highway 89 project, the California Department of Transportation (Caltrans) announced today.

The $70.1 million water-quality improvement project is building new drainage facilities to collect and treat stormwater runoff, adding curbs and gutters, widening the highway and repaving an eight-mile section of Highway 89 between Tahoma and Tahoe City. Work this season will focus on the remaining four miles of the project between Eagle Rock and Granlibakken Road.

Lake Tahoe area roadwork schedule for April 17 - 23

LONG-TERM PROJECTS

State Route 89 (Placer County): Work is set to resume on a $70.1 million project from Tahoma to just north of Granlibakken Road in Tahoe City that is upgrading storm water drainage and treatment systems, adding curb and gutter, resurfacing and realigning the road, adding new left-turn pockets and widening shoulders on an 8-mile stretch of the highway. Completion is expected by spring 2017.

Roadwork returns in South Lake Tahoe

SHORT-TERM PROJECTS

U.S. Highway 50 (El Dorado County) from Chiapa Drive to Kyburz Avenue: Motorists can expect intermittent full highway closures at various locations from 8 a.m. to 5 p.m. Monday through Friday for survey work.

U.S. Highway 50 (El Dorado County) from Truckee Drive to Rubicon Trail/Carson Avenue in South Lake Tahoe: Eastbound and westbound motorists can expect the #2 lane and right shoulder closed from 7 a.m. to 7 p.m. Monday through Thursday for utility work.

Opinion: Future of South Shore’s revitalization on the line

The South Shore of Lake Tahoe is divided by lines. These state, county, and city lines work well on a map, but they do not define the day-to-day reality of the people who live and work in this community. In the last decade we have seen definitive projects reshape South Shore – Heavenly Village, Lakeview Commons, Harrison Avenue Streetscape. We have seen new bike trails and the opening of a bi-state park.

Parents’ Co-op – Handling Difficult Behaviors

Event Date: 
February 3, 2016 - 6:00pm

The Kings Beach Parents’ Co-op hosts a series of parenting classes and meetings on the SNC Tahoe campus on the first Wednesday of every month. Classes are from 6-7 pm, followed by meetings from 7-8 pm, and are free and open to the public. Upcoming topics include:

Feb. 3:
Handling Difficult Behaviors
Mar. 2:
Love, Logic, and Personal Electronic Devices
Apr. 6:
Open Forum

For more information: http://www.sierranevada.edu/event/parents-co-op-handling-difficult-behaviors/

Location

Sierra Nevada College
999 Tahoe Blvd
United States
39° 14' 42.4176" N, 119° 56' 14.802" W

Federal funds aiding wildfire preparedness at Tahoe

The latest round of funding through the U.S. Bureau of Land Management’s Southern Nevada Public Land Management Act (SNPLMA) includes more than $3 million for projects to help reduce wildfire risk in Lake Tahoe communities.

The funding award for Lake Tahoe is part of nearly $40 million going to projects around Nevada to reduce wildfire risk, conserve landscapes, restore wildlife habitat, and improve public recreation. U.S. Secretary of the Interior Sally Jewell announced the funding awards this January.

TRPA releases draft active transportation plan for Tahoe

Improving transportation options for bicyclists and pedestrians is one of the most effective strategies to conserve and restore Lake Tahoe’s environment, revitalize the economy, enhance recreation opportunities, and improve public health, according to Tahoe Regional Planning Agency (TRPA) officials.

Opinion: Progress continuing at Lake Tahoe

People at Lake Tahoe are working together like never before to restore our environment, revitalize our economy, and improve our communities. We saw significant progress all around the lake this year. And our progress is sustainable with continued partnership and collaboration, so critical to tackle the many challenges and important decisions on our horizon.

Placer County pulls out of A & A Lake Tahoe Inn deal

Placer County has made two attempts to buy lodging properties in South Lake Tahoe to give them needed tourist accommodation units (TAUs) for future redevelopment projects in the North Lake Tahoe town centers of Kings Beach and Tahoe City.

The county had offered the owners of the A & A motel $1.425 million for their property at 3520 Lake Tahoe Blvd. After demolishing the motel, the county would have restored the land beneath, earning a bonus ratio of three-to-one TAUs from the Tahoe Regional Planning Agency, so the motel's 34 units would have been worth 102 to Placer County.

Lake Tahoe road work schedule for December 7 - 12

Work on all Lake Tahoe basin projects is either suspended for the season or completed. Here is an update on all projects. There is still road work being done on a stretch of Highway 50 in El Dorado Hills:

Prescribed burns to continue in Lake Tahoe basin next week

North Lake Tahoe Fire Protection District, the Nevada Division of Forestry and the U.S. Forest Service will continue widespread prescribed fire operations beginning the week of November 30, 2015.

Operations are planned for the following areas:

57 acres on urban lots on the west side of Incline Village. Smoke expected to travel North/Northeast/East.

28 acres off Fairway Drive near Tahoe City. Smoke expected to travel North/Northeast/East.

105 acres in Lake Tahoe Nevada State Park north of Spooner Lake. Smoked expected to travel Northeast.

Lake Tahoe road work schedule for November 22-28

Because of the Thanksgiving holiday, most lane closures will be restricted from 6 a.m. Wednesday, November 25 until 8 p.m. Sunday, November 29.

LONG-TERM PROJECTS

Lake Tahoe road work schedule for November 15-21

LONG-TERM PROJECTS

State Route 89 (Placer County): Work is in winter suspension on a $70.1 million project from Tahoma to the "Y" junction with State Route 28 in Tahoe City on Lake Tahoe’s West Shore that will upgrade storm water drainage and treatment systems, add curb and gutter, resurface and realign the road, add new left-turn pockets and widen shoulders on a 9-mile stretch of the highway. Completion is expected in fall 2016.

Lake Tahoe road work schedule for November 8 - 14

LONG-TERM PROJECTS

State Route 89 (Placer County): Work continues on a $70.1 million project from Tahoma to the "Y" junction with State Route 28 in Tahoe City on Lake Tahoe’s West Shore that will upgrade storm water drainage and treatment systems, add curb and gutter, resurface and realign the road, add new left-turn pockets and widen shoulders on a 9-mile stretch of the highway. Completion is expected in fall 2016.

Lake Tahoe road work schedule for November 1 - 7

LONG-TERM PROJECTS

State Route 89 (Placer County): Work continues on a $70.1 million project from Tahoma to the "Y" junction with State Route 28 in Tahoe City on Lake Tahoe’s West Shore that will upgrade storm water drainage and treatment systems, add curb and gutter, resurface and realign the road, add new left-turn pockets and widen shoulders on a 9-mile stretch of the highway. Completion is expected in fall 2016.

Lake Tahoe road work schedule for October 25 - 31

LONG-TERM PROJECTS

State Route 89 (Placer County): Work continues on a $70.1 million project from Tahoma to the "Y" junction with State Route 28 in Tahoe City on Lake Tahoe’s West Shore that will upgrade storm water drainage and treatment systems, add curb and gutter, resurface and realign the road, add new left-turn pockets and widen shoulders on a 9-mile stretch of the highway. Completion is expected in fall 2016.

Lake Tahoe road work schedule for October 18 - 24, 2015

LONG-TERM PROJECTS

State Route 89 (Placer County): Work continues on a $70.1 million project from Tahoma to the "Y" junction with State Route 28 in Tahoe City on Lake Tahoe’s West Shore that will upgrade storm water drainage and treatment systems, add curb and gutter, resurface and realign the road, add new left-turn pockets and widen shoulders on a 9-mile stretch of the highway. Completion is expected in fall 2016.

Nevada Highway Patrolman killed in Lake Tahoe in 1975 honored

The date was October 14, 1975. Tropper Gary Gifford was on duty for the Nevada Highway Patrol when the First National Bank of Nevada in Round Hill was robbed. The armed gunman escaped and left by car on Highway 50 towards Cave Rock. At noon, just before the tunnel, Tropper Gifford pulled over the robbery suspect.

There was an altercation between Gifford and the suspect when the tropper was shot and killed. The suspect was able to force another man to drive him around the lake to Kings Beach where he took four people hostage. Later that evening the suspect surrendered to authorities.

Lake Tahoe road work schedule for October 11 - 17, 2015

LONG-TERM PROJECTS

State Route 89 (Placer County): Work continues on a $70.1 million project from Tahoma to the "Y" junction with State Route 28 in Tahoe City on Lake Tahoe’s West Shore that will upgrade storm water drainage and treatment systems, add curb and gutter, resurface and realign the road, add new left-turn pockets and widen shoulders on a 9-mile stretch of the highway. Completion is expected in fall 2016.

FBI classifies North Tahoe/Incline Village church vandalism as hate crimes

The FBI and Placer County Sheriff’s Office are seeking the public’s help in identifying the person or persons responsible for vandalizing churches in the North Lake Tahoe area.

Between April 4 and September 14, 2015, multiple churches were vandalized, including one in Kings Beach and one in Tahoe City. One religious statue and exterior walls were spray-painted with offensive statements. Detectives are working with the Washoe County Sheriff’s Office, which has also had several churches vandalized in the Incline Village area.

Lake Tahoe road work schedule for October 5-10, 2015

LONG-TERM PROJECTS

State Route 89 (Placer County): Work continues on a $70.1 million project from Tahoma to the "Y" junction with State Route 28 in Tahoe City on Lake Tahoe’s West Shore that will upgrade storm water drainage and treatment systems, add curb and gutter, resurface and realign the road, add new left-turn pockets and widen shoulders on a 9-mile stretch of the highway. Completion is expected in fall 2016.

Lake Tahoe road work schedule for September 27 - October 3

LONG-TERM PROJECTS

State Route 89 (Placer County): Work continues on a $70.1 million project from Tahoma to the "Y" junction with State Route 28 in Tahoe City on Lake Tahoe’s West Shore that will upgrade storm water drainage and treatment systems, add curb and gutter, resurface and realign the road, add new left-turn pockets and widen shoulders on a 9-mile stretch of the highway. Completion is expected in fall 2016.

South Shore projects win TRPA's Best in Basin Awards

Several South Lake Tahoe projects were awarded this week by the Tahoe Regional Planning Agency (TRPA) as being the "Best in the Basin" for demonstrating exceptional planning, design, and compatibility with Lake Tahoe’s environment and communities.

The projects that were recognized upgraded highways, built new bike trails, improved water quality, restored environmentally-sensitive areas, remodeled blighted commercial buildings, and created defensible space for better wildfire protection.

The Best in the Basin award winners are:

Effects of winter storms on clarity of Lake Tahoe topic of upcoming workshops

Event Date: 
October 13, 2015 - 6:00pm

Everyone hopes for a winter of big storms at Lake Tahoe. Recent media hype evokes images of a "Godzilla" El Niño. But for Tahoe, big storms come with big impacts to Lake clarity as snowmelt and stormwater runoff transport pollutants and fine sediment into the Lake.

So how do Tahoe communities protect the Lake from big storm events?

IRONMAN Lake Tahoe runs 'last leg'; will not return to region

Lake Tahoe competition is on its last leg, according to event officials.

IRONMAN has given an emailed statement to News 4, explaining that organizers chose not to return to Lake Tahoe due to weather and environmental conditions.

Lake Tahoe road work schedule for September 20 - 26, 2015

LONG-TERM PROJECTS
State Route 89 (Placer County): Work continues on a $70.1 million project from Tahoma to the "Y" junction with State Route 28 in Tahoe City on Lake Tahoe’s West Shore that will upgrade storm water drainage and treatment systems, add curb and gutter, resurface and realign the road, add new left-turn pockets and widen shoulders on a 9-mile stretch of the highway. Completion is expected in fall 2016.

Lake Tahoe road work schedule for September 13 - 19, 2015

LONG-TERM PROJECTS

State Route 89 (Placer County): Work continues on a $70.1 million project from Tahoma to the "Y" junction with State Route 28 in Tahoe City on Lake Tahoe’s West Shore that will upgrade storm water drainage and treatment systems, add curb and gutter, resurface and realign the road, add new left-turn pockets and widen shoulders on a 9-mile stretch of the highway. Completion is expected in fall 2016.

Lake Tahoe road work schedule for September 6 - September 12

LONG-TERM PROJECTS

State Route 89 (Placer County): Work continues on a $70.1 million project from Tahoma to the "Y" junction with State Route 28 in Tahoe City on Lake Tahoe’s West Shore that will upgrade storm water drainage and treatment systems, add curb and gutter, resurface and realign the road, add new left-turn pockets and widen shoulders on a 9-mile stretch of the highway. Completion is expected in fall 2016.

Lake Tahoe road work schedule for August 30 - September 5

LONG-TERM PROJECTS

State Route 89 (Placer County): Work continues on a $70.1 million project from Tahoma to the "Y" junction with State Route 28 in Tahoe City on Lake Tahoe’s West Shore that will upgrade storm water drainage and treatment systems, add curb and gutter, resurface and realign the road, add new left-turn pockets and widen shoulders on a 9-mile stretch of the highway. Completion is expected in fall 2016.

Lake Tahoe road work schedule for August 23 - August 29

LONG-TERM PROJECTS

State Route 89 (Placer County): Work continues on a $70.1 million project from Tahoma to the "Y" junction with State Route 28 in Tahoe City on Lake Tahoe’s West Shore that will upgrade storm water drainage and treatment systems, add curb and gutter, resurface and realign the road, add new left-turn pockets and widen shoulders on a 9-mile stretch of the highway. Completion is expected in fall 2016.

Lake Tahoe road work schedule for August 16 - 22

LONG-TERM PROJECTS

State Route 89 (Placer County): Work continues on a $70.1 million project from Tahoma to the "Y" junction with State Route 28 in Tahoe City on Lake Tahoe’s West Shore that will upgrade storm water drainage and treatment systems, add curb and gutter, resurface and realign the road, add new left-turn pockets and widen shoulders on a 9-mile stretch of the highway. Completion is expected in fall 2016.

Lake Tahoe road work schedule for August 9 - 15

LONG-TERM PROJECTS
State Route 89 (Placer County): Work continues on a $70.1 million project from Tahoma to the "Y" junction with State Route 28 in Tahoe City on Lake Tahoe’s West Shore that will upgrade storm water drainage and treatment systems, add curb and gutter, resurface and realign the road, add new left-turn pockets and widen shoulders on a 9-mile stretch of the highway. Completion is expected in fall 2016.

Lake Tahoe road work schedule for August 2 - 8

LONG-TERM PROJECTS

State Route 89 (Placer County): Work continues on a $70.1 million project from Tahoma to the "Y" junction with State Route 28 in Tahoe City on Lake Tahoe’s West Shore that will upgrade storm water drainage and treatment systems, add curb and gutter, resurface and realign the road, add new left-turn pockets and widen shoulders on a 9-mile stretch of the highway. Completion is expected in fall 2016.

Understanding & Managing Micro-Irrigation Class

Event Date: 
August 4, 2015 - 5:30pm

Tahoe Resource Conservation District, in partnership with South Tahoe Public Utility District, is hosting FREE Water Conservation Workshops this summer.

The next one on the schedule is "Understanding and Implementing Micro-irrigation."

Lake Tahoe road work schedule for July 27 - August 1

LONG-TERM PROJECTS
State Route 89 (Placer County): Work continues on a $70.1 million project from Tahoma to the "Y" junction with State Route 28 in Tahoe City on Lake Tahoe’s West Shore that will upgrade storm water drainage and treatment systems, add curb and gutter, resurface and realign the road, add new left-turn pockets and widen shoulders on a 9-mile stretch of the highway. Completion is expected in fall 2016.

Lake Tahoe road work schedule for July 20 - July 25

Long Term Projects

State Route 89 (Placer County): Work continues on a $70.1 million project from Tahoma to the "Y" junction with State Route 28 in Tahoe City on Lake Tahoe’s West Shore that will upgrade storm water drainage and treatment systems, add curb and gutter, resurface and realign the road, add new left-turn pockets and widen shoulders on a 9-mile stretch of the highway. Completion is expected in fall 2016.

New power lines being installed between Martis Creek and Northstar

Liberty Utilities will begin construction to upgrade its existing 650 electrical line on or around August 3. Prior to this date, the public may see materials staged and vegetation management activities occur in preparation for the project.

Lake Tahoe road work schedule for July 12-18

LONG-TERM PROJECTS

State Route 89 (Placer County): Work continues on a $70.1 million project from Tahoma to the "Y" junction with State Route 28 in Tahoe City on Lake Tahoe’s West Shore that will upgrade storm water drainage and treatment systems, add curb and gutter, resurface and realign the road, add new left-turn pockets and widen shoulders on a 9-mile stretch of the highway. Completion is expected in fall 2016.

Lake Tahoe road work schedule for June 29 - July 2

Due to the increase of travelers expected in the Lake Tahoe basin, all road work projects will end for the week on Thursday, July 2.

On the South Shore:

Crews at nine small lightning caused fires near Lake Tahoe

There are nine small lightning caused fires currently burning in or around the Lake Tahoe Basin, the largest one is one-half acre in size.

Staff from the U.S. Forest Service is at each scene with firefighters from the Tahoe-Douglas and North Lake Tahoe Fire Protection Districts, working to extinguish them. Most of the fires are single-tree fires with some ground fire.

Winds are calm, and the Lake Tahoe Basin received substantial rainfall in the area of the fire starts, so the rate of spread is low.

Lake Tahoe road work schedule for June 21 - June 27

Here is a list of road projects around the Lake Tahoe basin.

U.S. Highway 50 (El Dorado County) from the junction with State Route 89 to 2nd Street in South Lake Tahoe: Eastbound motorists can expect alternating lane closures from 7 p.m. to 7 a.m. Monday through Friday for gas line relocation work. Eastbound motorists can also expect the right shoulder closed at the same location from 7 a.m. to 7 p.m. for trenching.

North Shore forest thinning to close off 340 acres during work hours

Thinning of trees for fuels reduction and forest health has resumed on approximately 340 acres of National Forest System lands on the east side of Highway 267 north of Speckled Avenue above Kings Beach.

Syndicate content